Cause: We believe we have sufficient water volume based on the system size however, when many zones close the size of the available volume can shrink. As a result, there may not be enough water volume. When the system size with the smallest zone open is not enough volume a buffer tank must be added.
Effect: Lack of water volume may be the result of too small system piping or a result of buffer tanks being too small as they may be sized for comfort cooling in a commercial application. Commercial systems require more volume than comfort systems.
Cause: Lack of water volume due to buffer tanks on the drawings being forgotten.
Effect: Lack of water volume will cause units to short cycle and eventually compressor failure. Ensure maximum and minimum loads are noted.
Cause: System sized with maximum water temperatures
Cause: Operating units when there is little or no load as the system will cycle, this often occurs on startup or commissioning. If the heat pump is oversized, meaning the capacity output from the unit cannot be transferred, the unit sees it as a low load condition.
Cause: Bad electrical system in the building
Effect: Lose compressors due to rapid restarting and stopping.
Cause: Oversized pumps or hydronics are not balanced.
Cause: Low water flow rate on primary loop, incorrect pump size, dirty strainer, hydronic system not balanced or designed improperly.
Cause: The heat exchanger is undersized.
Cause: Resetting alarms.
Cause: Units installed with variable flow on the chilled water and/or hot water side.
Cause: Below minimum water flow rate for a given unit.
Cause: Working at the compressor limit or outside the limits.